TECHNICAL SPECIFICATIONS FOR THE INCINERATOR
1. SCOPE OF WORK The work specified in the contract will include. 
1. Supply, install and commission an incinerator as provided in the technical specifications 
2. Provision for adherence to OSHA and other statutory requirement relating to Health and Safety of workers during execution of the works covered in this tender. 
3. Assessment and preparation and construction of a standard incinerator shed with one waste storage room ( see the design ) 

4. Provision of operation and maintenance manuals and drawings complete with maintenance schedule and instructions. 

5. Fuel oil storage tank- Mild steel1500 liters capacity 

6. Onsite training for operation and maintenance staff. 

auto on/off burner
Auto temperature
-excess air blower fan
Chamber constructed of two layer refractory lining, compressing:
Thermal insulator lining & refractory masonry lining sufficient enough to maintain normal temperature at outside
Control Panel
Standard PLC Control
Note: All the instruments/controllers must be of high quality. Preferably European/Japanese origin
Chimnery/Stack
-Made of MS Sheet. Sufficiently insulated & lined with refractory bricks(where required) to maintain normal temperature at outer surface
-painted with high quality
-customer will be responsible for provision of electric supply and natural gas uot in incinerator
Heat and corrosion resistant paint.
Note:
Motors of all blowers/fans/pumps must be high quality, preferably imported(Japanese. European std)